Safer roads - A592
In Summer 2018, the Council were granted £7.4 million from the Department for Transport (DfT) to upgrade and improve the safety of the A592 from Windermere to the A66 near Rheged.
Since 2018, the Council has undertaken extensive survey works on the A592 route to identify where and how best to invest the funding in the highway and to improve road safety.
Following design development work, a number of individual resurfacing schemes were completed late January 2023 supporting the next phase of the Programme.
Kirkstone Pass works
This next key stage of work on the A592 is between Windermere and Rheged on Kirkstone Pass. These improvements began in early February 2023 with the bulk of the work concluding in July 2024. This was by the far the most challenging aspect of the planned work on the A592 owing to the location, the geography, the steepness of the route and the susceptibility to weather conditions.
The duration and timescale for completion of all the proposed works on Kirkstone Pass takes account of the scope, the scale and complexity. The planned completion date is likely to be Friday 18 October 2024. Further details are provided in frequently asked questions and points below.
The below maps highlight the location of the planned work:
Scheme extent using what3words:
Start of A592 works (north end): Brother’s Water: desktop.activates.risks
End of A592 works (south end): Hird Wood: sapping.pinches.myth
Frequently asked questions and points
A592 Kirkstone Pass - Patterdale to Troutbeck FAQs (PDF 250KB)
Dates | Duration | Temporary Traffic Management Arrangements (including planned works) |
---|---|---|
13/02/23 onwards | 3 weeks | Daytime Traffic Signals (CCTV surveys, drain repairs, retaining wall repairs, new signs, carriageway haunching + other works) |
06/03/23 onwards | 4 weeks | Full Road Closure No. 1 (new drainage crossings and associated works, carriageway resurfacing works, boundary wall repairs) |
05/06/23 onwards | 4 weeks | Full Road Closure No. 2 (safety barrier works) |
03/07/23 | Approx. 2 weeks | Overnight road closures from 9pm until 7am |
02/10/23 onwards | 3 weeks | Full Road Closure No. 3 (carriageway reconstructions and patching) |
04/03/24 | Until 28 March 2024 | Full Road Closure No. 4 (Completion of civils work) |
30/10/23 | Approx. 3 weeks | Overnight road closures from 9pm until 7am |
06/12/23 | Approx. 2 weeks | Overnight road closures from 9pm until 7am |
03/01/24 | Approx. 2½ weeks | Overnight road closures from 9pm until 7am |
16/04/24 | 2 weeks | Full Road Closure No. 5 (carriageway resurfacing on the North side of the Pass) |
01/05/2024 | 1 day | The contractor has experienced two lost working days due to poor weather over the course of the last 2 weeks which has significantly impacted on the tonnage of material that needed to be laid. The contractor will therefore require an additional day’s closure to conclude the remaining surfacing and complete the North side fully. |
07/10/24 | 2 weeks | Full road closure No. 6 (carriageway construction) |
A592 Temporary diversion route: (during both the full road closures as well as overnight road closures)
Kirkstone Pass A592 safer roads improvements update - June 2023 - YouTube
A592 Kirkstone Pass safer roads improvements flyover video
Kirkstone Pass Road Safety Improvements Works - Drone Footage from Metcalfes (YouTube)